Project at a glance
DestinationIndonesia
Capacity rangeSet by the order
Configurationfilling equipment
Productfilling equipment
What is includedSupply, factory test, shipping, commissioning
RecordOrder and delivery notes below

What was ordered?

From the 4th to the 7th of June, SUNSWELL Machinery participated in the PPP EXPO Plastic Packaging Printing and Food Processing Equipment Exhibition in Indonesia.

What was non-standard about the project?

As we all know, Indonesia is the world's largest archipelago country, with its territory spanning Asia and Oceania. It has a very advantageous shipping location in Southeast Asia. Its capital, Jakarta, is the largest city in Southeast Asia and the economic center of Indonesia. Indonesia has a population of over 300 million and has a huge development market and development potential. At the same time, China is Indonesia's largest trading partner.

StationFunction in the line
PackingSecondary packaging

Site requirements, air and water consumption sit with the Gravity Filling Machine for Still Water.

What does the delivery record show?

At this exhibition, most of the customers came from Indonesia. Not have very high requirements for equipment capacity. Most of the inquiries were for small capacity equipment. Of course, also have some powerful local companies. Our agents in the Indonesian market also actively participated in the reception of customers at the exhibition, giving us great support and help. In addition, through the publicity work before the exhibition, we also successfully met with several interested customers. I believe that SUNSWELL MACHINERY will have the opportunity to open up new market at Indonesia in future.

Site requirements, air and water consumption sit with the Volumetric Filling Machine for Still Water.

Frequently asked questions

What does the order cover?

The order covers supply, factory test, shipping and commissioning, configured with filling equipment. The line was specified for filling equipment.

What capacity was specified, and what should the plant plan on?

Set by the order at the format named on the order. Rated figures exclude changeover, CIP and downstream stops, so plan production on 0.65-0.85 of that number.

What was non-standard about the project?

The non-standard items are the ones recorded in the section above. Everything else follows the standard configuration for filling equipment.

How is the line handed over?

Factory acceptance test before shipment, then installation and commissioning on site. Operator training is part of the handover, not an extra.

What is covered after handover?

Spare parts for the wear items, remote support, and a commissioning report that records the settings the line was left running at.

Key takeaways
  1. Indonesia took delivery of a line rated Set by the order, configured for filling equipment.
  2. Scope ran from factory test to commissioning: supply, factory test, shipping and commissioning.
  3. The non-standard items are listed above rather than left to the order correspondence.
About the author
Written by the Sunswell engineering team - led by Howie SUN, Founder & CEO, with 14 years in filling and blow-moulding equipment R&D and turnkey project delivery across 71+ countries.
Last reviewed: 2026-08-28 . Reviewed by Sunswell engineering team
×

Contact Us

captcha

*We respect your privacy. When you submit your contact information, we agree to only contact you in accordance with our Privacy Policy.

×

Inquire

*Name
*Email
Company Name
Phone/Whatsap
*Message

*We respect your privacy. When you submit your contact information, we agree to only contact you in accordance with our Privacy Policy.