A device on the conveyor is only worth its cost if the line stops when it stops, or the defect rate rises when it is off. However, over time, carbonation levels can decrease due to factors such as temperature changes and exposure to oxygen.
Key facts at a glance
What is includedPrinters, coders, cap feeders, nitrogen dosers, detectors
FunctionSupport the filler without changing its rating
Key controlPosition, timing, consumable cost
IntegrationSignals from the filler PLC or a standalone sensor
Key decisionWhether the device earns its cost per 1,000 units
Typical positionAfter the filler, before the packer

Where does it sit in the line sequence?

Position follows the signal. A coder needs the bottle presented at a fixed gap; a cap feeder needs a buffer before the capper; a detector needs a clear view and a reject gate downstream. Moving any of them changes the timing and the reject logic.

What consumable cost does it add per 1,000 units?

Ink, solvent, laser power, nitrogen, caps and labels all carry a per-unit cost that does not appear in the machine price. A device with a low purchase price and a high consumable cost can be the most expensive item on the line over five years.

DeviceWhat it controlsConsumable
Coder or printerDate and batch codeInk, solvent or laser power
Cap feederCap supply to the capperNone, but a buffer is needed
Nitrogen doserHeadspace oxygenNitrogen per 1,000 units
Fill level detectorReject decisionNone, but a reject gate is needed

Site requirements, air and power consumption sit with the Accessory.

How is it integrated with the filler?

Either through a discrete signal from the filler PLC, which is simple and reliable, or through the line network, which allows recipes and reporting. Discrete signals are easier to commission; network integration is easier to audit. Choose based on who will maintain it.

Site requirements, air and power consumption sit with the Conveying.

What should be checked at acceptance?

Run the device at the line rating, not at a demonstration speed, and count rejects with the device on and off. Acceptance at half speed hides the timing problem that appears in the first production week.

The same question is worked through from another angle in Blow Mould Quality: What a Buyer Should Check.

How is a coder synchronised with the conveyor?

Through an encoder on the conveyor, so the print position follows the actual speed rather than a set value. Without the encoder, the code stretches when the line accelerates and lands off-centre.

How to read the numbers. Treat the capacity figures as reference ranges from the product specification. Setup, adjustment and upstream stops sit outside a rated rate, so plan on 0.65-0.85.

Frequently asked questions

Can a detector reject without stopping the line?

Yes, with a reject gate and a shift register that tracks the bottle from the sensor to the gate. Without the register, the gate rejects the wrong bottle.

How does a laser coder differ from an inkjet coder?

A laser marks the surface and needs no consumable ink, but it needs a clear line of sight and a consistent bottle position. An inkjet prints on most surfaces and carries ink and solvent cost.

Why does a cap feeder jam?

Caps arrive out of orientation, the elevator runs faster than the chute can release, or the chute angle is wrong for the cap. Most jams are a chute and speed setting, not a cap defect.

Does a fill level detector need a reject gate?

Yes. Detection without a reject gate only records the defect. The gate needs a shift register so it rejects the bottle that was measured, not the one behind it.

Where should a nitrogen doser sit?

Between the filler and the closure, close enough that the gas stays in the headspace. Moving it further downstream wastes gas and gives an unstable result.

Key takeaways
  1. Support equipment removes a task or a defect; it does not add capacity.
  2. Position follows the signal path, not the convenience of the layout.
  3. Acceptance at production speed, not at demonstration speed.
  4. A device without a reject gate only records the defect.
About the author
Written by the Sunswell engineering team - led by Howie SUN, Founder & CEO, with 14 years in filling and blow-moulding equipment R&D and turnkey project delivery across 71+ countries.
Last reviewed: 2026-08-28 . Reviewed by Sunswell engineering team
×

Contact Us

captcha

*We respect your privacy. When you submit your contact information, we agree to only contact you in accordance with our Privacy Policy.

×

Inquire

*Name
*Email
Company Name
Phone/Whatsap
*Message

*We respect your privacy. When you submit your contact information, we agree to only contact you in accordance with our Privacy Policy.