Beverage Industry Productivity Benchmark: What OEE Level Should Your Plant Target?

Views: 322 Author: Howie SUN Publish Time: Update Time:
Filling equipment is chosen from the product and the package, and the machine follows: viscosity, acidity and carbonation pick the filling principle before BPH does. Yes within 6–12 months of ramp if changeover is designed in from the start on the Combiblock.

Combibloc for CSD & Sparkling Water by Mechanical Filler

Key facts at a glance
What is includedFilling, capping, labelling and packing equipment
Sizing basisDemand in units per day, divided by productive hours and a production factor
Production factor0.65-0.85 depending on formats and changeovers
Key controlFill accuracy, closure integrity, changeover time
Key decisionOne flexible line or two dedicated lines
AcceptanceOutput, accuracy, closure and changeover, measured

Where does a filling line lose output that the specification ignores?

Changeover, CIP, label roll changes and downstream stops. A line rated at 12,000 BPH and run with four formats and two changeovers per shift delivers closer to 8,000. The production factor is not a discount on the machine; it is what the plant actually gets.

What does the factory acceptance test actually prove?

It proves the machine meets the written specification on the agreed product, at the agreed format, in the builder workshop. It does not prove the line will run in your building. Both tests are needed, and the second one is where most disputes start.

DecisionWhat it fixesWhat it does not fix
Filling principleProduct and accuracyDownstream capacity
Valve countRated BPHChangeover and CIP time
Automation levelLabour per shiftProduct quality
Line layoutFloor space and flowThroughput of the slowest station

Where this becomes a line rather than a single machine, the Gravity Filling Machine for Still Water is the starting point.

How is automation level decided?

By the cost of the labour it replaces and the consistency it adds, not by the technology. A robot palletizer pays on three shifts with a stable pattern; it does not pay on one shift with five patterns. The same logic applies to inspection and packing.

Where this becomes a line rather than a single machine, the Volumetric Filling Machine for Still Water is the starting point.

What makes a commissioning run fail?

Utilities that are not ready, product that is not the real product, and operators who have not been trained. The machine is rarely the cause. A commissioning plan that lists utilities, product samples and training as prerequisites finishes on time far more often.

Yes within 6–12 months of ramp if changeover is designed in from the start on the Combiblock.

The same question is worked through from another angle in Filling precision analysis of high tank.

How to read the numbers. What the specification calls capacity is a reference range, not a tested output. Rated capacity is a steady-state number; changeover and cleaning sit outside it, so size on 0.65-0.85.

Frequently asked questions

How do I calculate the BPH I actually need?

Bottles per day divided by productive hours, then divided by a production factor of 0.65-0.85. The factor covers changeover, cleaning and downstream stops. Sizing at 1.0 is the most common planning error.

How long does a filling line last?

A well-maintained stainless line runs for well over a decade, with wear parts replaced on condition. The variables are water quality, cleaning regime and whether spare parts are kept in stock.

What is the difference between a monoblock and a full line?

A monoblock combines rinse, fill and cap on one frame. A full line adds treatment, blowing, labelling, packing and palletizing around it. The monoblock is one station in a longer chain.

How much production factor should I use for a new line?

Between 0.65 and 0.85. A single-format line on one shift sits near 0.85; a line with four formats and two changeovers per shift sits near 0.65.

Key takeaways
  1. Compare quotations on the slowest station, changeover and CIP time.
  2. The production factor is what the plant gets, not a discount.
  3. The factory test proves the specification, not the building.
  4. Buy the long-lead spares with the machine.
About the author
Written by the Sunswell engineering team - led by Howie SUN, Founder & CEO, with 14 years in filling and blow-moulding equipment R&D and turnkey project delivery across 71+ countries.
Last reviewed: 2026-08-28 . Reviewed by Sunswell engineering team
×

Contact Us

captcha

*We respect your privacy. When you submit your contact information, we agree to only contact you in accordance with our Privacy Policy.

×

Inquire

*Name
*Email
Company Name
Phone/Whatsap
*Message

*We respect your privacy. When you submit your contact information, we agree to only contact you in accordance with our Privacy Policy.