The Importance of Regular Calibration in Maintaining Fill Accuracy

Views: 1788 Author: Howie SUN Publish Time: Update Time:
Filling equipment is chosen from the product and the package, and the machine follows: viscosity, acidity and carbonation pick the filling principle before BPH does.
Key facts at a glance
What is includedFilling, capping, labelling and packing equipment
Sizing basisDemand in units per day, divided by productive hours and a production factor
Production factor0.65-0.85 depending on formats and changeovers
Key controlFill accuracy, closure integrity, changeover time
Key decisionOne flexible line or two dedicated lines
AcceptanceOutput, accuracy, closure and changeover, measured

When should a plant buy two lines instead of one flexible line?

When the formats are far apart, or when one product cannot tolerate the cleaning regime of the other. A single flexible line carries changeover cost every day; two dedicated lines carry capital cost once. The crossover is usually visible in the annual changeover hours.

What belongs in the acceptance protocol?

Rated output at the specified format, fill accuracy on a defined sample, closure torque or seam measurement, and a full changeover timed with the customer watching. Anything not measured at acceptance becomes a discussion after the money is paid.

DecisionWhat it fixesWhat it does not fix
Filling principleProduct and accuracyDownstream capacity
Valve countRated BPHChangeover and CIP time
Automation levelLabour per shiftProduct quality
Line layoutFloor space and flowThroughput of the slowest station

The Gravity Filling Machine for Still Water is the reference unit for this configuration.

How should a line layout be reviewed before signing?

At 1:100, with conveyor radii, maintenance access and the largest format drawn in. Most layout problems appear as a service door that cannot open or a pallet that cannot turn. Fixing them on paper costs nothing; fixing them on site costs weeks.

Where this becomes a line rather than a single machine, the Volumetric Filling Machine for Still Water is the starting point.

Which spare parts should be bought with the machine?

One full set of valve seals, one set of capping inserts, guide rail blocks and the change parts for the second format. These are the items with long lead times that stop a line for days. Buying them with the machine is cheaper than buying them in a hurry.

The same question is worked through from another angle in The Importance of Proper Installation and Leveling of Heavy.

How to read the numbers. Rated capacity in this note follows the product specification range, not a factory acceptance test. Changeover, cleaning and downstream stops are not inside a rated BPH, so plan with a production factor of 0.65-0.85.

Frequently asked questions

How do I calculate the BPH I actually need?

Bottles per day divided by productive hours, then divided by a production factor of 0.65-0.85. The factor covers changeover, cleaning and downstream stops. Sizing at 1.0 is the most common planning error.

How long does a filling line last?

A well-maintained stainless line runs for well over a decade, with wear parts replaced on condition. The variables are water quality, cleaning regime and whether spare parts are kept in stock.

What drives the price of a filling line?

Valve count, automation level, material of construction, whether blowing is included, and the packing format. Price follows the specification, so two quotes are only comparable when the specifications match.

How much production factor should I use for a new line?

Between 0.65 and 0.85. A single-format line on one shift sits near 0.85; a line with four formats and two changeovers per shift sits near 0.65.

Key takeaways
  1. Anything not measured at acceptance becomes a later argument.
  2. The factory test proves the specification, not the building.
  3. Two quotes are comparable only when the specifications match.
  4. Ask for the FAT procedure before the price.
About the author
Written by the Sunswell engineering team - led by Howie SUN, Founder & CEO, with 14 years in filling and blow-moulding equipment R&D and turnkey project delivery across 71+ countries.
Last reviewed: 2026-08-28 . Reviewed by Sunswell engineering team
×

Contact Us

captcha

*We respect your privacy. When you submit your contact information, we agree to only contact you in accordance with our Privacy Policy.

×

Inquire

*Name
*Email
Company Name
Phone/Whatsap
*Message

*We respect your privacy. When you submit your contact information, we agree to only contact you in accordance with our Privacy Policy.