The Benefits of Touchscreen HMIs and PLC Control in Modern Filling Equipment

Views: 2101 Author: Howie SUN Publish Time: Update Time:
Two quotations that look different usually differ in four numbers: the slowest station, the changeover time, the CIP time and the consumable cost. Touchscreen HMIs coupled with PLC control systems enable advanced recipe management capabilities in filling equipment.
Key facts at a glance
ScopeFilling, capping, labelling and packing equipment
Sizing basisDemand in units per day, divided by productive hours and a production factor
Production factor0.65-0.85 depending on formats and changeovers
Key controlFill accuracy, closure integrity, changeover time
Key decisionOne flexible line or two dedicated lines
AcceptanceOutput, accuracy, closure and changeover, measured

How do you compare two quotations that look different?

Compare the lowest rated station, the changeover time, the CIP time and the consumable cost per 1,000 units. A lower price with a slower packer or a longer CIP is not a lower cost. Ask both suppliers for the same four numbers in writing.

Where does a filling line lose output that the specification ignores?

Changeover, CIP, label roll changes and downstream stops. A line rated at 12,000 BPH and run with four formats and two changeovers per shift delivers closer to 8,000. The production factor is not a discount on the machine; it is what the plant actually gets.

Automation features enabled by PLC systems optimize production processes, reducing manual intervention and increasing overall throughput.

DecisionWhat it fixesWhat it does not fix
Filling principleProduct and accuracyDownstream capacity
Valve countRated BPHChangeover and CIP time
Automation levelLabour per shiftProduct quality
Line layoutFloor space and flowThroughput of the slowest station

The specification sheet for the Gravity Filling Machine for Still Water carries the utility figures quoted here.

When should a plant buy two lines instead of one flexible line?

When the formats are far apart, or when one product cannot tolerate the cleaning regime of the other. A single flexible line carries changeover cost every day; two dedicated lines carry capital cost once. The crossover is usually visible in the annual changeover hours.

The Volumetric Filling Machine for Still Water is the matching unit when this becomes a line project.

Which spare parts should be bought with the machine?

One full set of valve seals, one set of capping inserts, guide rail blocks and the change parts for the second format. These are the items with long lead times that stop a line for days. Buying them with the machine is cheaper than buying them in a hurry.

The same question is worked through from another angle in Order from another customer Costa Rican customer.

How to read the numbers. The capacity figures here are reference ranges taken from the product specification. A rated figure assumes one format and no cleaning stops. Plan on 0.65-0.85 to cover changeover, CIP and downstream stoppages.

Frequently asked questions

What is the difference between BPH and bottles per minute?

BPH is bottles per hour; divide by 60 for bottles per minute. A 12,000 BPH line runs at 200 bottles per minute, and every downstream machine has to carry that rate.

How long does a filling line last?

A well-maintained stainless line runs for well over a decade, with wear parts replaced on condition. The variables are water quality, cleaning regime and whether spare parts are kept in stock.

What drives the price of a filling line?

Valve count, automation level, material of construction, whether blowing is included, and the packing format. Price follows the specification, so two quotes are only comparable when the specifications match.

How do I verify a supplier before ordering?

Ask for the factory acceptance test procedure, a reference line running the same format, and the spare parts list with lead times. A supplier who cannot show a running line has not commissioned many.

Key takeaways
  1. Fix the product and the package before the machine.
  2. The production factor is what the plant gets, not a discount.
  3. Buy the long-lead spares with the machine.
  4. Ask for the FAT procedure before the price.
About the author
Written by the Sunswell engineering team - led by Howie SUN, Founder & CEO, with 14 years in filling and blow-moulding equipment R&D and turnkey project delivery across 71+ countries.
Last reviewed: 2026-08-28 . Reviewed by Sunswell engineering team
×

Contact Us

captcha

*We respect your privacy. When you submit your contact information, we agree to only contact you in accordance with our Privacy Policy.

×

Inquire

*Name
*Email
Company Name
Phone/Whatsap
*Message

*We respect your privacy. When you submit your contact information, we agree to only contact you in accordance with our Privacy Policy.