| Typical duty | Still water, RO water, mineral water |
| Valve type | Gravity or volumetric valve |
| Capacity range | 5,000-48,000 BPH at 500 ml |
| Bottle sizes | 200 ml to 16 L, by configuration |
| Material | SUS 304 product contact, CIP-ready |
| Line scope | Treatment, blowing, filling, capping, labelling, packing |
A water line stands or falls on three inputs: raw water analysis, neck finish, and how well filler and capper are matched. BPH takes the meeting; the neck finish and the capper match get the last five minutes. Rinser clamps and capping heads are cut for one neck finish; a 1 mm thread change means new change parts rather than a new machine.
Mineral water is defined by its source and its mineral profile, so treatment is limited to what the label claim allows. Purified water starts from any feed and is built up to a specification. The filling machine is the same; the treatment train and the legal claim are not.
| Filling principle | Best for | Watch out for |
|---|---|---|
| Gravity | Still water, one rigid bottle size | Thin-wall bottles deform under head pressure |
| Volumetric valve | 3-15 L and mixed formats | Valve wear shows as slow drift, not a sudden error |
| Isobaric | Carbonated water only | Needs counter-pressure, so slower per valve |
| Load cell | Oil and high-value liquid | Slower cycle, higher cost per valve |
Site requirements, air and water consumption sit with the Blow-fill-cap Combibloc for Still Water.
A small line gives up automation, not quality. Manual or semi-automatic packing, fewer accumulation buffers, and a simpler CIP usually follow. What it should not give up is the filling valve and the capping head, because those two decide whether the product is saleable.
Throughput and change-part lists are on the Gravity Filling Machine for Still Water page rather than in this note.
A monoblock carries the rinser, the filler and the capper on one frame with one drive. It removes two transfers, the floor space between them and the bottle handling at each. Three separate machines are easier to replace one at a time and easier to run at different rates.
The same question is worked through from another angle in Water Filling Machines for Glass Bottles: Special Considerations.
Yes, with change parts: star wheels, guide rails, grippers and a filling recipe. Budget 40-90 minutes per switch and expect the production factor to drop from about 0.85 to 0.70.
Plan for 380 V three-phase power, 0.6-0.8 MPa compressed air, and a chiller if blow molding runs in-house. Exact consumption belongs in the utility schedule of the quotation, not in a rule of thumb.
Not on the same filler. Carbonation needs isobaric valves, a CO2 dosing and mixing unit, and a different bowl. A combiblock can carry both valve sets, but they are separate specifications, not a field conversion.
Commercial practice is a stated band per bottle size, typically checked by weight at the filler outlet. The band belongs in the acceptance protocol. A line without a written tolerance will argue about it at commissioning.
Country: Maldives
Product: PET Bottled Mineralized Water
Capacity: 24,000BPH (500ml); 2 Lines
Solution:Water Production Line
Country:Kazakhstan
Product: PET Bottled Sparkling Water, Canned Soft Drink, Canned Tea
Capacity: 25000CPH (250ml)
Solution:Three Lines,7000BPH(1.5L), 15000CPH(330ml),15000CPH(450ml)