| Where it fits | Still water, RO water, mineral water |
| Filling principle | Gravity or volumetric valve |
| Capacity | 5,000-48,000 BPH at 500 ml |
| Format range | 200 ml to 16 L, by configuration |
| Material | SUS 304 product contact, CIP-ready |
| Line scope | Treatment, blowing, filling, capping, labelling, packing |
Raw water, neck finish and the filler-capper match decide more about a water line than its BPH. Most of the meeting goes on BPH; the other two get a fraction of the time. Rinser clamps and capping heads are cut for one neck finish; a 1 mm thread change means new change parts rather than a new machine.
Work backwards from cases per day. Divide bottles per day by productive hours, then divide again by a production factor of 0.65-0.85. The factor covers changeover, CIP, label roll changes and downstream stops. Sizing at 1.0 is the most common and most expensive mistake in a water project, because the shortfall only appears once the line is running.
| Filling principle | Best for | Watch out for |
|---|---|---|
| Gravity | Still water, one rigid bottle size | Thin-wall bottles deform under head pressure |
| Volumetric valve | 3-15 L and mixed formats | Valve wear shows as slow drift, not a sudden error |
| Isobaric | Carbonated water only | Needs counter-pressure, so slower per valve |
| Load cell | Oil and high-value liquid | Slower cycle, higher cost per valve |
A different bottle format means a different unit; see the Blow-fill-cap Combibloc for Still Water.
Ask for the rated capacity of the slowest station, the changeover checklist, the CIP cycle time, and the water and power consumption per 1,000 bottles. Those four numbers decide the real cost per bottle. A quotation that lists only the filler capacity and a total price leaves the buyer comparing incomparable offers.
Rated output, change parts and services are listed on the Gravity Filling Machine for Still Water page.
Mineral water is defined by its source and its mineral profile, so treatment is limited to what the label claim allows. Purified water starts from any feed and is built up to a specification. The filling machine is the same; the treatment train and the legal claim are not.
The same question is worked through from another angle in How to Set Up a Complete Water Filling Line.
Temperature, valve wear and bottle variation, in that order. Water is less sensitive than oil, but a warm product foams more and a worn valve closes late. Weighing a sample every few hours catches the drift before it reaches the customer.
Yes, with change parts: star wheels, guide rails, grippers and a filling recipe. Budget 40-90 minutes per switch and expect the production factor to drop from about 0.85 to 0.70.
It follows the raw water analysis, not a standard package. Surface water usually needs multi-media filtration, RO and UV or ozone. Low-hardness municipal water may need only carbon filtration and disinfection.
It depends on whether blowing, packing and palletizing sit in the same hall. Fix the footprint by drawing the layout at 1:100 with conveyor radii included, then check the turning radius of the largest format.
Plan for 380 V three-phase power, 0.6-0.8 MPa compressed air, and a chiller if blow molding runs in-house. Exact consumption belongs in the utility schedule of the quotation, not in a rule of thumb.
For a complete line with blowing, filling, labelling and packing, plan several weeks on site after arrival, plus operator training. Civil work and utility readiness are the usual delay, not the machinery.
Country: Maldives
Product: PET Bottled Mineralized Water
Capacity: 24,000BPH (500ml); 2 Lines
Solution:Water Production Line
Country:Kazakhstan
Product: PET Bottled Sparkling Water, Canned Soft Drink, Canned Tea
Capacity: 25000CPH (250ml)
Solution:Three Lines,7000BPH(1.5L), 15000CPH(330ml),15000CPH(450ml)