| Product fit | Still water, RO water, mineral water |
| Filling principle | Gravity or volumetric valve |
| Capacity | 5,000-48,000 BPH at 500 ml |
| Bottle range | 200 ml to 16 L, by configuration |
| Contact material | SUS 304 product contact, CIP-ready |
| Line scope | Treatment, blowing, filling, capping, labelling, packing |
Raw water, neck finish and the filler-capper match decide more about a water line than its BPH. Most of the meeting goes on BPH; the other two get a fraction of the time. Rinser clamps and capping heads are cut for one neck finish; a 1 mm thread change means new change parts rather than a new machine.
Equipped with programmable logic controllers (PLCs) and touch screen interfaces, allowing for precise control and easy operation.
Work backwards from cases per day. Divide bottles per day by productive hours, then divide again by a production factor of 0.65-0.85. The factor covers changeover, CIP, label roll changes and downstream stops. Sizing at 1.0 is the most common and most expensive mistake in a water project, because the shortfall only appears once the line is running.
| Filling principle | Best for | Watch out for |
|---|---|---|
| Gravity | Still water, one rigid bottle size | Thin-wall bottles deform under head pressure |
| Volumetric valve | 3-15 L and mixed formats | Valve wear shows as slow drift, not a sudden error |
| Isobaric | Carbonated water only | Needs counter-pressure, so slower per valve |
| Load cell | Oil and high-value liquid | Slower cycle, higher cost per valve |
The Blow-fill-cap Combibloc for Still Water is the reference unit for this configuration.
Mineral water is defined by its source and its mineral profile, so treatment is limited to what the label claim allows. Purified water starts from any feed and is built up to a specification. The filling machine is the same; the treatment train and the legal claim are not.
Sizing for this duty runs through the Gravity Filling Machine for Still Water, where the valve count is set out.
A water line is cleaned on a fixed cycle plus a changeover clean. The circuit covers the filler bowl, the product pipes and the filling valves. Ozone or heat is used for disinfection, and the cycle time is a planned stop rather than an incident.
The same question is worked through from another angle in How to Choose Between Gravity, Pressure, and Volumetric Filling.
Yes, with change parts: star wheels, guide rails, grippers and a filling recipe. Budget 40-90 minutes per switch and expect the production factor to drop from about 0.85 to 0.70.
It follows the raw water analysis, not a standard package. Surface water usually needs multi-media filtration, RO and UV or ozone. Low-hardness municipal water may need only carbon filtration and disinfection.
Plan for 380 V three-phase power, 0.6-0.8 MPa compressed air, and a chiller if blow molding runs in-house. Exact consumption belongs in the utility schedule of the quotation, not in a rule of thumb.
Not on the same filler. Carbonation needs isobaric valves, a CO2 dosing and mixing unit, and a different bowl. A combiblock can carry both valve sets, but they are separate specifications, not a field conversion.
Country: Maldives
Product: PET Bottled Mineralized Water
Capacity: 24,000BPH (500ml); 2 Lines
Solution:Water Production Line
Country:Kazakhstan
Product: PET Bottled Sparkling Water, Canned Soft Drink, Canned Tea
Capacity: 25000CPH (250ml)
Solution:Three Lines,7000BPH(1.5L), 15000CPH(330ml),15000CPH(450ml)