How to Prevent Electrostatic Discharge in PET Bottling Lines

Views: 2273 Author: Howie SUN Publish Time: Update Time:
Filling equipment is chosen from the product and the package, and the machine follows: viscosity, acidity and carbonation pick the filling principle before BPH does. These additives work by enhancing the conductivity of the PET material, allowing static charges to dissipate more efficiently.
Key facts at a glance
What is includedFilling, capping, labelling and packing equipment
Sizing basisDemand in units per day, divided by productive hours and a production factor
Production factor0.65-0.85 depending on formats and changeovers
Key controlFill accuracy, closure integrity, changeover time
Key decisionOne flexible line or two dedicated lines
AcceptanceOutput, accuracy, closure and changeover, measured

How do you compare two quotations that look different?

Compare the lowest rated station, the changeover time, the CIP time and the consumable cost per 1,000 units. A lower price with a slower packer or a longer CIP is not a lower cost. Ask both suppliers for the same four numbers in writing.

What belongs in the acceptance protocol?

Rated output at the specified format, fill accuracy on a defined sample, closure torque or seam measurement, and a full changeover timed with the customer watching. Anything not measured at acceptance becomes a discussion after the money is paid.

DecisionWhat it fixesWhat it does not fix
Filling principleProduct and accuracyDownstream capacity
Valve countRated BPHChangeover and CIP time
Automation levelLabour per shiftProduct quality
Line layoutFloor space and flowThroughput of the slowest station

Site requirements, air and water consumption sit with the Gravity Filling Machine for Still Water.

What does the factory acceptance test actually prove?

It proves the machine meets the written specification on the agreed product, at the agreed format, in the builder workshop. It does not prove the line will run in your building. Both tests are needed, and the second one is where most disputes start.

Sizing for this duty runs through the Volumetric Filling Machine for Still Water, where the valve count is set out.

How should a line layout be reviewed before signing?

At 1:100, with conveyor radii, maintenance access and the largest format drawn in. Most layout problems appear as a service door that cannot open or a pallet that cannot turn. Fixing them on paper costs nothing; fixing them on site costs weeks.

The same question is worked through from another angle in Order for 3 lines from Kazakhstan.

What is the difference between capacity and throughput?

Capacity is what the machine can do at steady state in one format. Throughput is what the plant gets across a week of changeovers, cleaning and stops. Plans built on capacity alone are the reason new lines look slow in their first month.

These additives work by enhancing the conductivity of the PET material, allowing static charges to dissipate more efficiently.

How to read the numbers. What the specification calls capacity is a reference range, not a tested output. Changeover, cleaning and downstream stops are not inside a rated BPH, so plan with a production factor of 0.65-0.85.

Frequently asked questions

How do I calculate the BPH I actually need?

Bottles per day divided by productive hours, then divided by a production factor of 0.65-0.85. The factor covers changeover, cleaning and downstream stops. Sizing at 1.0 is the most common planning error.

How long does a filling line last?

A well-maintained stainless line runs for well over a decade, with wear parts replaced on condition. The variables are water quality, cleaning regime and whether spare parts are kept in stock.

Can a line be upgraded later?

Capacity is usually added by a second line or by a downstream upgrade, not by speeding up the filler. The filler, the capper and the packer are matched, so raising one alone moves the bottleneck.

What drives the price of a filling line?

Valve count, automation level, material of construction, whether blowing is included, and the packing format. Price follows the specification, so two quotes are only comparable when the specifications match.

How do I verify a supplier before ordering?

Ask for the factory acceptance test procedure, a reference line running the same format, and the spare parts list with lead times. A supplier who cannot show a running line has not commissioned many.

Key takeaways
  1. Fix the product and the package before the machine.
  2. Compare quotations on the slowest station, changeover and CIP time.
  3. Anything not measured at acceptance becomes a later argument.
  4. The factory test proves the specification, not the building.
About the author
Written by the Sunswell engineering team - led by Howie SUN, Founder & CEO, with 14 years in filling and blow-moulding equipment R&D and turnkey project delivery across 71+ countries.
Last reviewed: 2026-08-28 . Reviewed by Sunswell engineering team
×

Contact Us

captcha

*We respect your privacy. When you submit your contact information, we agree to only contact you in accordance with our Privacy Policy.

×

Inquire

*Name
*Email
Company Name
Phone/Whatsap
*Message

*We respect your privacy. When you submit your contact information, we agree to only contact you in accordance with our Privacy Policy.