Project Planning · Combiblock Series

Combiblock Plant Layout and Footprint Planning

Size the building from zone allocations, not machine envelopes — and calculate storage before you sign for the land.

1,100-2,450
Covered area, one 12,000 BPH line
5-8 m
Clear height under structure
30-40 de caramelos
Presión de aire que sopla
20,000
Instalación de fabricación
444+
Líneas entregadas

Respuesta corta: A single 12,000 BPH PET bottling line needs roughly 310-455m² of production hall, 185–340 m² of utility rooms and 80–160 m² of personnel areas. Storage is calculated from days of cover and typically adds 500–1,500 m², giving a covered building of about 1,100–2,450 m² plus yard. Clear height should be 5–8 m, and a combiblock removes the air conveyor and empty bottle buffer entirely.

🎯 Conclusiones clave

  1. Plan from zone allocation, not machine envelope — add about 30% over operating envelopes for aisles and maintenance access
  2. A 12,000 BPH line needs roughly 1,100–2,450 m² covered, of which storage is usually the largest single item
  3. 5 m clear height is the minimum, 6–8 m is comfortable; height is cheap before the steelwork is ordered and expensive afterwards
  4. Cast the drainage before the slab is finished — trench drains and a 1:100 fall in the wet zone, sized for a CIP dump
  5. Size storage from consumption: 240,000 preforms a day at 12,000 BPH over 20 hours, and several hundred pallet movements out
  6. A second line does not double the building — utilities are largely shared, so size the utility rooms for the final line count on day one

1. Read a footprint number correctly

Almost every layout argument on a bottling project starts with two people using the word "footprint" to mean different things. Before any area is discussed, separate three figures that are routinely confused:

  1. Sobre de máquina. The outline on the general arrangement drawing. It is the smallest of the three and the only one a supplier can state precisely.
  2. Operating envelope. The envelope plus the space to open guard doors, withdraw a mould, change format parts, stand at the operator panel and roll a trolley past. Typically the envelope plus one metre on the access sides and considerably more where a mould or a carousel has to come out.
  3. Zone allocation. The operating envelope plus the share of aisle, buffer and circulation the machine imposes on the hall. This is the number that decides how big the building must be.

Plan the building from the third figure. A layout drawn from machine envelopes fits on paper and then fails on the first mould change, when there is nowhere to put the mould. As a working rule, add about 30% to the sum of operating envelopes for circulation and maintenance access in the production hall, and check that number against the specific withdrawal directions marked on each foundation drawing.

2. Indicative footprint for a 12,000 BPH PET line

The table below is an estimating tool for a single blow-fill-cap line producing 1.5 L PET still water at 12,000 BPH on a 20-hour day. It is indicative and depends on configuration; use it to size a building enquiry, then replace each line with the real drawing as the specification firms up.

Zona Indicative area ¿Qué lo impulsa?
Preform and closure feeding 20 m² Hopper, elevator, unscrambler and the octabin position beside it
Blow-fill-cap bloque combinado, with access 90-120m² Machine envelope plus mould withdrawal and service side
Etiquetado 15-20m² Label technology and reel change access
Codificación e inspección 6-10m² Coder, level and cap inspection, reject station
Conveying and accumulation 40-70m² Distance between machines and how much buffer you design in
embalaje retráctil 25-35m² Pack format and film reel handling
Palletising and pallet handling 45-70m² Robot or layer palletiser, pallet magazine, full pallet outfeed
Circulation and maintenance aisles 70-110m² About 30% of the above; forklift routes decide the minimum
Production hall subtotal 310-455m² One line, single storey
Water treatment room 60-120m² Entirely dependent on source water analysis and tank sizes
Compressed air room 40-70m² High-pressure blowing air at 30–40 bar, low-pressure service air, dryers, receivers
Chilled water and cooling 25-45m² Mould cooling duty and ambient design temperature
Electrical and control room 20-35m² Transformer position, switchgear and cable routing
CIP skid and chemical store 20-35m² Tank count, bunding and safe chemical handling
Laboratorio de calidad 20-35m² Test scope and whether microbiology is done in-house
Utility subtotal 185-340m² Shared if a second line is added later
Changing, welfare and offices 80-160m² Headcount and hygiene zoning
Almacenamiento de materias primas y productos terminados 500-1,500m² Days of cover — calculated in section 5
Covered total ~1,100–2,450 m² One 12,000 BPH line with modest storage cover
External yard, tanks, effluent, standby power 400-900m² Truck turning circle usually dominates

A second line does not double the building. The production hall roughly repeats, but water treatment, compressed air, chilled water, laboratory and welfare are largely shared and grow far less than proportionally. Plants that expect to add capacity should size the utility rooms and the incoming services for the final line count on day one, and leave the hall extendable in one direction.

3. The building shell

3.1 Clear height

Five metres clear under any structure over the line is the practical minimum, six to eight metres is comfortable. Height is consumed by preform elevators, by service platforms on the block, by conveyor bridges and by a palletiser lifting a full pallet. Storage areas with racking need their own figure. Height is also the cheapest thing to buy before the steelwork is ordered and the most expensive thing to add afterwards.

Piso 3.2

Three properties matter, in this order. Carga: design against the point loads on each foundation drawing, with a heavier allowance under racking legs and stacked pallets than under the machines themselves. Planitud: within roughly 2 mm under a 2 m straightedge in the machine area, so the block can be levelled without excessive grouting. Curar: a slab poured late and loaded early is a recurring cause of alignment problems, so the concrete programme has to be finished before installation begins, not during it.

3.3 Drenaje

The wet zone — rinser, filler, CIP return, any cooling or washdown — needs trench drains with removable grating and a floor fall toward them of roughly 1:100. Size the drain for a CIP dump plus washdown at the same time, not for a slow trickle. Cutting drainage into a finished slab after the machines are standing on it costs several times what it costs to cast in.

3.4 Getting the machine in

The block arrives in sections and the largest crate decides the door opening, the internal route and the lifting plan. Check crate dimensions and weights against the door, the internal column grid and the floor along the route before shipment. A temporary wall opening is a normal and inexpensive solution when it is planned; it is neither when it is discovered on the day the truck arrives. Sequence detail is in envío, instalación y puesta en marcha.

4. Utility rooms and where to put them

Utility rooms are usually drawn last and regretted first. Four of them have position requirements, not just area requirements.

  • Aire comprimido. High-pressure blowing air at 30–40 bar is the largest single energy consumer on a PET line, and pressure drop in a long high-pressure run is paid for continuously. Keep the room close to the block, separate it acoustically, and size it for the air receivers, the dryer and the heat the compressors reject.
  • Low-pressure air. A separate 7–8 bar supply serves pneumatics, capping, conveying and packing. Running everything from the high-pressure machine through a regulator wastes energy on every cubic metre.
  • Agua helada. Mould cooling needs reliable flow at a stable temperature. Size against the largest bottle and the hottest month, and place the plant so pipe runs are short. Consumption figures are discussed in combiblock energy and utility consumption.
  • Tratamiento de aguas. Position it upstream of the hall with its raw and treated water tanks, and give it room for the treatment train the water analysis actually calls for. Scope and area are set by the analysis, not by the line speed — see water treatment for beverage production.
  • Electrical room. Dry, ventilated, away from washdown zones, with a planned cable route to the line rather than an improvised one.

5. Size storage from consumption, not from habit

Storage is the largest and most frequently underestimated part of a bottling plant. Do the arithmetic rather than picking a number.

5.1 entrante

A 12,000 BPH line running 20 hours consumes roughly 240,000 preforms and 240,000 closures a day, plus label and film reels. Preforms arrive in octabins holding on the order of 25,000–35,000 units each depending on preform weight, so that is around seven to ten octabins a day. Multiply by your intended days of cover, allow for stacking and forklift aisles, and the inbound store sizes itself. Import lead times and customs variability usually push this figure higher than a domestic supply chain would.

5.2 Saliente

The same line produces roughly 360 m³ of product a day at 1.5 L. Converted to pallets that is several hundred pallet movements daily, and each day of cover is a substantial block of floor at any realistic stacking height. Most plants hold two to five days and dispatch the balance directly, which makes the loading dock and the truck yard part of the storage calculation rather than an afterthought.

Count the trucks, then size the yard. A single mid-capacity water line generates enough finished-goods volume to fill more than a dozen trucks a day. If the yard cannot turn that number of vehicles, the warehouse fills up and the line stops — a stoppage caused entirely by civil design.

6. Flow, zoning and the things auditors check

Two flows have to be drawn separately on the layout, and a third has to be drawn on top of them.

  1. Flujo de materiales. Ideally one direction: raw material in at one end, finished goods out at the other. Where the building forces a U shape, keep incoming and outgoing routes physically separated rather than sharing an aisle.
  2. Personnel flow. A single controlled entry into the production hall, through changing and hand washing. Not the same door the forklifts use.
  3. Hygiene zoning. Higher-care areas around the filler and the closure path, with defined boundaries, appropriate finishes and controlled access. Draw the boundary line on the layout; if it is not on the drawing it will not exist on site.

Two practical additions that are cheap on paper and expensive later: a maintenance workshop and spare parts store within reach of the line, and a laydown area where a mould set or a carousel section can be placed during a changeover. Plants that omit both end up doing maintenance in the aisle.

7. What a combiblock removes from the layout

The layout case for a block is stronger than the machine-envelope comparison suggests, because the deleted items are spread out rather than concentrated.

Item on a separate blower + filler line On a combiblock Layout consequence
Air conveyor between blower and filler No presente Removes a long overhead run, its supports and the floor space beneath it
Empty bottle accumulation No presente Empty bottles occupy large volume for their value; buffering them needs real area
Empty bottle store, where bottles are bought in No presente Frequently the largest single storage item a plant can delete
Two machine foundations and two control cabinets Uno de cada uno Shorter cable and pipe routes, one operator position
Air conveyor blower units and their air demand No presente Smaller low-pressure air room and less noise in the hall

On a greenfield site this shows up as a smaller building. On a retrofit into leased or existing space it is often the reason the project is feasible at all. The quantified comparison, including manpower and running cost, is in Bloque combinado frente a línea de soplado y llenado separada.

8. Layout sequence, and the mistakes that cost most

Work in this order. Each step constrains the next, and reversing any two of them creates rework:

  1. Fix the production plan. Formats, output and operating hours. Everything downstream is sized from this.
  2. Commission the water analysis. Treatment scope and its room size follow from it, and it takes weeks to obtain.
  3. Select the line configuration and obtain general arrangement and foundation drawings, including withdrawal directions.
  4. Calculate storage from consumption and days of cover, including the truck yard.
  5. Draw the zones, then the flows, then the utility rooms.
  6. Check the shell: clear height, column grid, floor design, drainage, door openings and the route in.
  7. Freeze the layout and issue it for civil design, then run civil works in parallel with equipment manufacturing.

The recurring mistakes are consistent across projects: sizing the building from machine envelopes instead of zone allocations; leaving drainage out until the slab is poured; under-sizing the utility rooms so the second line cannot be added; putting a column where the block has to stand; forgetting the mould withdrawal direction; and treating finished goods storage as spare space rather than as a calculated area. Sunswell has supplied repeat-line plants where this planning is visible in the result, including four 12,000 BPH 1.5 L lines for Taza and eight bottling and canning lines for Rauan, both in Kazakhstan. Capacity-driven sizing is covered in Selección de capacidad del bloque combinado, and the wider equipment map in the complete beverage filling equipment guide.

Preguntas frecuentes

How much space does a bottling line need?

For one 12,000 BPH PET line, budget roughly 310–455 m² for the production hall itself, 185–340 m² of utility rooms and 80–160 m² for personnel areas. Storage is calculated separately from days of cover and usually adds 500–1,500 m², giving a covered building of roughly 1,100–2,450 m².

What clear height does a PET bottling hall need?

Five metres clear is the practical minimum under any structure over the line. Six to eight metres is better, because preform elevators, the block's own service platforms and a palletiser stacking full pallets all reach upward. Storage areas with racking need more again — specify height before the steelwork is ordered.

What floor loading and flatness are required?

Design the slab against the point loads on the machine foundation drawing rather than a general figure, and allow more under racking legs and under full pallets. Flatness in the machine area should be within about 2 mm under a 2 m straightedge, with levelling plates and grout taking up the rest.

How much floor space does a combiblock save?

The saving is not only the machine envelope. A block deletes the air conveyor run, the empty bottle accumulation and, in many plants, an empty bottle store — and each of those is floor area that would otherwise sit between the blower and the filler. On a constrained site that is often the deciding argument.

Where should the compressed air room go?

Close enough to the block that the high-pressure pipe run is short, because pressure drop in a long 30–40 bar line is paid for in energy every hour the line runs. Far enough away, or acoustically separated, that the noise does not sit on top of the operators. Ventilation and heat rejection decide the room size as much as the machines do.

How many days of raw material and finished goods should I store?

It depends on supply reliability and dispatch frequency, not on a rule. Calculate consumption first: a 12,000 BPH line running 20 hours consumes around 240,000 preforms and closures a day. Then decide how many days of that you must hold, and convert to floor area at your own stacking height.

Can I install a bottling line in an existing building?

Often yes, and it is worth checking before building new. The constraints that decide it are clear height, the column grid, the door opening against the largest crate, floor condition and whether drainage can be cut into the slab. Send a dimensioned building drawing with the enquiry rather than a photograph.

Should people and materials use the same doors?

No. Separate personnel entry, with changing and hand washing on the route into the production hall, from the material and pallet routes. Keep incoming raw material and outgoing finished goods on different paths where the building allows it. Retrofitting this separation after an audit is far more expensive than drawing it correctly.

Acerca del autor.

Escrito por el equipo de ingeniería de Sunswell, liderado por Howie solFundador y director ejecutivo, con 14 años de experiencia en I+D de equipos de llenado y moldeo por soplado, y en la entrega de proyectos llave en mano en más de 71 países.

Última revisión: 07/08/2026 · Revisado por el equipo de ingeniería de Sunswell

Obtenga una propuesta de configuración

Indíquenos su producto, el número de botellas por hora (BPH) objetivo, el tamaño de las botellas y los detalles de la preforma. Le enviaremos un plano de diseño.

No enviamos spam. Respondemos por correo electrónico.

Datos clave de un vistazo
Las cosechadoras Moldeo por soplado + llenado + sellado (3 en 1)
CAPACIDAD 2,000 - 48,000 BPH
Tamaños de botella 0.2 – 16 L PET
Productos Agua sin gas, refrescos, zumo, té, aceite comestible, cuidado del hogar
Válvulas de llenado Célula de carga / volumétrica / mecánica / semieléctrica
Operador 1 persona para todo el bloque

¿Tienes algún proyecto específico en mente?

Indíquenos el producto, el objetivo de botellas por hora, el tamaño de las botellas y el mercado objetivo. Le enviaremos un borrador del diseño, una lista de equipos y una estimación del plazo de entrega.

×

Contáctenos

Captcha

*Respetamos tu privacidad. Cuando envía su información de contacto, aceptamos contactarlo solo de acuerdo con nuestro Política de Privacidad.

×

Preguntar

*Nombre
*Correo electrónico
Nombre de la Empresa
Teléfono/WhatsApp
*Mensaje

*Respetamos tu privacidad. Cuando envía su información de contacto, aceptamos contactarlo solo de acuerdo con nuestro Política de Privacidad.