water bottling line


Last time we mentioned that on July 13th, Sunswell have already had one 5000BPH Water Bottling Line installation and commissioning at the Maldives customer’s factory. This time Sunswell’s engineers team went to another island for 10000BPH Water Filling Whole Line. And another two lines of Blowing-Filling-Capping Combiblock for water now is still under production in our factory.


Our engineers team arrived on island on 25th July for installation and commissioning of the machines. As the special nature of Maldives, the tools and equipment there are not so perfect as expected, which caused our plan a little lag. However, our engineers tried everything to solve the problems , After the few days, the installation of all machines has been finished finally.


our team are solving the problem


10000BPH Water Filling Whole Line we provided for Maldives includes the following systems:

1.  Water Treatment

2.  Air Compressor

3.  Rotary Blowing Machine (8 Cavity Capacity can reach 10000BPH)

4.  Water Filling Machine  

     XGF24Rising-24Filling-6Capping 500ml Capacity can reach 10000BPH

5.  Hot Melt Glue Labeling Machine

6.  Conveyor System

7.  Shrink Wrapping Machine


a group photo


Since the installation and commissioning has already completed successfully, I surely believe that this 10000BPH Water Filling Line will be put into production in the near future.